Our Development Program

At Loreburn Housing Association, our vision is to create GREAT places to live, providing new energy efficient homes for our customers.

Our Development Team are working with the Scottish Government to help meet their targets of 50,000 new homes by 2021 and we have committed to delivering 350 new homes over the next 3 years in order to help the Scottish Government meet their target. To finance this new development programme Loreburn Housing Association receive Government funding through the Council’s Strategic Housing Investment Plan and we have also secured private finance to help back our extensive programme.

This is a very exciting time for the Development Team as we have identified a need for a variety of different housing provisions region wide. Along side our great quality of general purpose family homes, we are looking in to developing Extra Care developments, Dementia friendly properties and Dementia communities. Just recently we have received planning permission for the first Foyer in Dumfries and Galloway. Our first major achievement in our new development programme going forward.

Development Team   Brooke Street Site

Development Update 

Site

Units

Property Mix

Type 

Lead Officer

Stage

 

 

The Garrick, Stranraer

 

 

25

Foyer

4 x 2 Bed & 8, 1 Bed Dementia Friendly Flats

6 x 2 Bed Flats for young People

4 x 2 Bed Wheelchair Bungalows

1 x 4 Bed Bungalow

 

 

Mixed

 

 

Scott Anderson

 

Works Underway -

Handover Expected April 2021

 

 

 

 

 

 

 

Station Road, Annan

 

9

 

Mixture of 1 & 2 Bed Flats

Supported

 

Scott Anderson

Works Underway -

Handover Expected November 2020

 

 

 

 

 

 

 

Academy Street, Castle Douglas

 

23

 

Mixture of 1 & 2 Bed Flats

Supported (Older People)

 

Scott Anderson 

Planning Application Approved.

In final detailed design stage.

 

 

 

 

 

 

 

 

Longmeadow House, Annan 

 

 

 

 

27

 

 

 

8 x 2 Bed Semi-Detached/Terraced Houses

6 x 3 Bed Semi-Detached/terraced Houses

6 x 2 Bed Amenity Bungalows

4 x 1 Bed Amenity Bungalows

1 x 4 Bed Terraced House

1 x 4 Bed Wheelchair Friendly House

1 x 2 Bed Autism Friendly House

 

 

Mainstream

 

 

TBC

 

Planning Permission received

 

 

 

 

 

 

 

 

Woodlands Drive, Lochmaben

 

 

6

 

 

6 x 3 Bed Semi-Detached Houses

 

 

 

 

Mainstream

 

 

Denise Carr

 

Await update on Planning Application

 

 

 

 

 

 

 

Selkirk Road, Moffat

 

73

 

20 x 2-bed Extra Care Bungalows

11 x 2-bed amenity Bungalows

 

Remainder  to be confirmed

 

Extra Care

 

Fiona Pennington

 

Masterplan submitted to DGC.   

Design Team are working on the detailed planning application for the site.

 

 

 

 

 

 

 

Murtholm, Langholm

 

100 tbc

 

Unit types to be confirmed

 

Extra Care

 

Fiona Pennington

 

Masterplan has been submitted to DGC.  Planning Application for Enabling Works submitted in August.

 

Design Team are working on planning application for 35 Extra Care & Amenity houses.  LHA seeking demand info for the rest of the site.  Locals are asked to register an interest at Loreburn Lettings

 

 

 

 

 

 

 

Herries Avenue, Heathhall

 

 

75

 

25 x 2 Bed Semi-Detached Homes

4 x 3 Bed Semi-Detached Homes

10 x 3 Bed Detached Homes

16 x 2 Bed Amenity Bungalows

4 x 1 Bed Amenity Bungalows

15 x 4 Bed Detached Homes

1 x 5 Bed Wheelchair House

 

Mainstream

 

Fiona Pennington

 

Phase 1A on site with 11 x 2-beds & 4 x 3-beds.  Completion expected Feb 2021.

Phase 1B – out to tender.  Expected on site around November 2020 with 4 x 1-bed bungalows, 14 x 2-beds, 16 x 2-bed bungalows, 10 x 3-beds, 15 x 4-beds & 1 x 5-bed houses.

 

 

 

 

 

 

 

Forsyth Street, Dumfries

 

4

 

4 x 3 Bed Semi-Detached Passiv Haus

 

Mainstream

 

Denise Carr

 

On site – Expected Handover November 2020

 

 

 

 

 

 

 

 

 

Lincluden Church

 

12

 

11 x 3 Bed Amenity Bungalows

1 x Staff Base

 

Supported

 

Denise Carr

Planning - application submitted

 

Proposed start date November 2020